I am pleased to announce that Practical Completion was achieved on the 7th July 2010 and would like to thank everyone involved who have assisted on this project. Especially our site staff of Mark Howell & Tommy Malloy who worked extremely hard. The project has been completed on time and to a very hight standard. The RLS are now in and operating and enjoying using their wonderful new facility and can report that everything is operating well. We were able to hand over the job defect free. Hope you enjoy some final photos of the finished project below. Planning to add a few more later once the centre is underway. Thanks, Garry Sundin
ROYAL LIFESAVING'S AQUATIC TRAINING ACADEMY, SEVEN HILLS
f
Thursday, July 29, 2010
Thursday, July 8, 2010
PRACTICAL COMPLETION DUE 7th JULY
With Practical Completion due on Wednesday 7th July the site is being prepared for handover. All the works have been completed and all services have been tested and commissioned. The pools are full, heated and ready for swimming. Royal Life have done much of their fitout and just about ready for operating. The centre is looking great and a tribute to all concerned especially our Site team of Mark Howell & Tommy Malloy. We have some final photos to come and a short video to revisit the whole project. We shall keep you all posted when these are available. Enjoy a few of our recent photos below from 2nd to 6th July.
Thursday, July 1, 2010
COMPLETION TIME IS HERE
The end is now well and truly in sight with just the last of the finishing touches being applied both inside and out. With only a few days left we are finalisng all the paperwork with Blacktown Council and other authorities to provide the RLS with their Occupation Certficate. Everythin is being done in anticipation of the new centre being officially handed over on Wednesday 7th July 2010. It's lookig great and my thanks to all those that were part of the project. Special thanks to Site Manager Mark Howell and SIte Assistant Tommy Malloy for their hard work and attention to details. Well done boys. Also, thanks to the Howell family for the wonderful birthday cake. It was very well done and also very tasty ! Click here to veiw photos 20th June to 1st July
Sunday, June 20, 2010
FINISHING LINE IN SITE
Works are progressing along well despite the recent rains, which have seen some delays coasued to completing the external works of the carpark and landscaping. Inside all the finishing trades are now done and both pools have been filled. With the intial cleaning getting started and all the services being tested and commissioned we are gearing up for cpmpletion aroudn the end of June. Mark has the place looking good. Click here to see progress photos for period 5th to 18th June.
Monday, June 7, 2010
WATER APPEARS INSIDE & OUT
So we have some good news and some bad news. The good news is that we have finished the pool tiling and cleaned the pools and started to fill the pools with water, the bad news is we also have water outside coming down from the heavens and affected the external works. However generally the progress has been good especially internally where most of the finishes have been done and the pools now ready to fill. The carpark works and landscaping are affected by the rain and progress has been slowed. All in all Mark & Tommy have done a great job in keeping somewhere near on time. Click here to see all the progress photos from 19th May to 4th June below.
Tuesday, May 18, 2010
WHERE'S THE WATER ?
It's almost time to turn the taps on and start filling the pool. The progress continues to go well with the pool tiling almost completed and many of the finishing trades now done. With the joinery works jsut about finished and floor coverinsg underway the inside is really coming togther and loking great. The external works are also on the move with carpark works, tiling entry stairs and handrails all underwya. Landscaping works are due to start next week. Click here to view all the photos 5th to 18th May.
Tuesday, May 4, 2010
FINISHES PROGRESSING WELL
Mark & Tommy have the project progressing well with many of the finishing trades well advanced. With some colours being added by way fo the wall tiling and joinery units the internal areas are coming to life. Along with the tilers and joinery works are the painters,ceilings, doors and hardware all going well and looking good. Externally the carpark works have commenced along with the main entry landing tiling plus metal handrails have been measured. All remains on track for a June handover and opening. Click here to view all the photos 23rd April to 4th May.