Thursday, July 29, 2010

PRACTICAL COMPLETION !!

I am pleased to announce that Practical Completion was achieved on the 7th July 2010 and would like to thank everyone involved who have assisted on this project. Especially our site staff of Mark Howell & Tommy Malloy who worked extremely hard. The project has been completed on time and to a very hight standard. The RLS are now in and operating and enjoying using their wonderful new facility and can report that everything is operating well. We were able to hand over the job defect free. Hope you enjoy some final photos of the finished project below. Planning to add a few more later once the centre is underway. Thanks, Garry Sundin

Thursday, July 8, 2010

PRACTICAL COMPLETION DUE 7th JULY

With Practical Completion due on Wednesday 7th July the site is being prepared for handover. All the works have been completed and all services have been tested and commissioned. The pools are full, heated and ready for swimming. Royal Life have done much of their fitout and just about ready for operating. The centre is looking great and a tribute to all concerned especially our Site team of Mark Howell & Tommy Malloy. We have some final photos to come and a short video to revisit the whole project. We shall keep you all posted when these are available. Enjoy a few of our recent photos below from 2nd to 6th July.

Thursday, July 1, 2010

COMPLETION TIME IS HERE

The end is now well and truly in sight with just the last of the finishing touches being applied both inside and out. With only a few days left we are finalisng all the paperwork with Blacktown Council and other authorities to provide the RLS with their Occupation Certficate. Everythin is being done in anticipation of the new centre being officially handed over on Wednesday 7th July 2010. It's lookig great and my thanks to all those that were part of the project. Special thanks to Site Manager Mark Howell and SIte Assistant Tommy Malloy for their hard work and attention to details. Well done boys. Also, thanks to the Howell family for the wonderful birthday cake. It was very well done and also very tasty ! Click here to veiw photos 20th June to 1st July

Sunday, June 20, 2010

FINISHING LINE IN SITE

Works are progressing along well despite the recent rains, which have seen some delays coasued to completing the external works of the carpark and landscaping. Inside all the finishing trades are now done and both pools have been filled. With the intial cleaning getting started and all the services being tested and commissioned we are gearing up for cpmpletion aroudn the end of June. Mark has the place looking good. Click here to see progress photos for period 5th to 18th June.


Monday, June 7, 2010

WATER APPEARS INSIDE & OUT

So we have some good news and some bad news. The good news is that we have finished the pool tiling and cleaned the pools and started to fill the pools with water, the bad news is we also have water outside coming down from the heavens and affected the external works. However generally the progress has been good especially internally where most of the finishes have been done and the pools now ready to fill. The carpark works and landscaping are affected by the rain and progress has been slowed. All in all Mark & Tommy have done a great job in keeping somewhere near on time. Click here to see all the progress photos from 19th May to 4th June below.

Tuesday, May 18, 2010

WHERE'S THE WATER ?

It's almost time to turn the taps on and start filling the pool. The progress continues to go well with the pool tiling almost completed and many of the finishing trades now done. With the joinery works jsut about finished and floor coverinsg underway the inside is really coming togther and loking great. The external works are also on the move with carpark works, tiling entry stairs and handrails all underwya. Landscaping works are due to start next week. Click here to view all the photos 5th to 18th May.

Tuesday, May 4, 2010

FINISHES PROGRESSING WELL

Mark & Tommy have the project progressing well with many of the finishing trades well advanced. With some colours being added by way fo the wall tiling and joinery units the internal areas are coming to life. Along with the tilers and joinery works are the painters,ceilings, doors and hardware all going well and looking good. Externally the carpark works have commenced along with the main entry landing tiling plus metal handrails have been measured. All remains on track for a June handover and opening. Click here to view all the photos 23rd April to 4th May.

Thursday, April 22, 2010

COLOURS BEING REVEALED

With the good progress of tiling, painting, joinery and other finishes the internal colour scheme is started to come to life. Works during this period have seen good progress with a number of the finishing trades including the start of joinery and also plumbing fittings. The pool tiling progress is good along with the pool acosutic ceilings. Outside the carpark works have commemced.
Click here to view the photos for period 13th to 22nd April

Wednesday, April 14, 2010

START TO GET THE COSIES READY

The progress on site is moving along well with the pool halls really starting to come to life. With the acoustic ceilings well underway and pool tiling proceeding and other finishing trades advancing along it will not be to long before the water can start to go in. The services trades are also well advanced with light fittings and Airconditioning systems being installed. Mark, Tommy and all the subbies are doing a great job,
Click here to see pics for works done from 2nd to 12th April

Wednesday, April 7, 2010

TIME FOR EASTER EGGS

As the Project heads into the Easter break (for some well earned easter egss) we see many signs of the finished product starting to appear. These are in the form of ceilings (to pools halls and all areas), wall & floor tiling, pool tiling, doors & door frames, painting, light fittings, airconditioning units and pool plant. Externally to the OSD tank is almost finished and the water tank installed. Mark & Tommy are continuing to do a good job with the progress while ensuring on delivering a high standard of quality. The project remains on track for a June completion.
Click Here for photos of works 20th March to 1st April

Tuesday, March 23, 2010

LET THE FINISHES BEGIN !

This weeks photos show some of the finishing works starting. This includes for the insulated wall panels to the pool hall walls, acoustic pool hall ceilings, ceramic tiling & painting. As well there are now some light fittings being installed. The external works continue to progress along with OSD tank base complete and the new ramp and path now concreted,. The job remains on target for a June completion.
Click here for Progress photos for 12th March to 19th March 2010

Thursday, March 11, 2010

MARK MAKES REAL PROGRESS

Mark & Tommy have pushed the project along really well over the last 10 days to get plenty of activities on the move and progressing well. The programme pool hall acoustic ceilings and wall linings are going well in order to start pool tiling soon.
All the internal walls and ceilings are nearly done with painting started. Externally the progress is now moving again after the rains and shoudl be ready for the carpark to start ealry April after Easter.
CLICK HERE TO CHECK OUT PROGRESS PHOTOS FOR THIS PERIOD 3rd to 11th MARCH

Thursday, March 4, 2010

PROGRESS ROLLS ALONG

Mark, Tommy and the boys on site have worked very hard to try and bring the project back on line after all the rain during February even as recent as last week. There have been a few unavoidable delays but generally things are moving along well. The internal areas are starting to come togther with some of the finishing trades like ceilings and tiling due to start in the next or so.
Please click here to check out recent Progress Pics from 17 Feb to 2 March

Wednesday, February 17, 2010

FEBRUARY RAINS AFFECT PROGRESS

Unfortunately the first couple of weeks of February have bought along unwanted rain to the site and affected the external works in particular, especially the OSD detention tank. Inside the works are proceeding with the wall framing and linings moving along well. Also the services are proceeding well with the Mechancial Services and Filtration systems both having major components delivered and installed.
Please click here to view photos 3rd to 16th February 2010

Thursday, February 4, 2010

THE FINISH IS IN SITE

Mark & Tommy are pushing the project along very well, and all areas of the site are well underway and heading towards the scheduled June 2010 completion date. Some recent rain has had a some effect of the external works and so the focus has been turned towards the inside. See following progress photos to bring you up to date with the works.
Click to here to view progress photos 22nd January to 2nd February 2010

Sunday, January 24, 2010

2010 Progress Starts well

The new year has started well with progress moving along inside and out. The building is now just about locked up with most of the glazing being completed and doors due on very soon. The internal wall linings and framing is proceeding at good pace togther with all the services being roughed-in. Mark has also moved ahead with the external works starting the new pathway, carpark and detention tank. See following pics for the works so far this year
Progress Photos 4th to 21st January 2010 - click here to view

Photos for the last few weeks of 2009 remain below for your viewing.