WHERE'S THE WATER ?

It's almost time to turn the taps on and start filling the pool. The progress continues to go well with the pool tiling almost completed and many of the finishing trades now done. With the joinery works jsut about finished and floor coverinsg underway the inside is really coming togther and loking great. The external works are also on the move with carpark works, tiling entry stairs and handrails all underwya. Landscaping works are due to start next week. Click here to view all the photos 5th to 18th May.