ROYAL LIFESAVING'S AQUATIC TRAINING ACADEMY, SEVEN HILLS

f

Sunday, June 20, 2010

FINISHING LINE IN SITE

Works are progressing along well despite the recent rains, which have seen some delays coasued to completing the external works of the carpark and landscaping. Inside all the finishing trades are now done and both pools have been filled. With the intial cleaning getting started and all the services being tested and commissioned we are gearing up for cpmpletion aroudn the end of June. Mark has the place looking good. Click here to see progress photos for period 5th to 18th June.


No comments:

Post a Comment